Align project resource requests to the project schedule (04:34)

Try It!

If there is a significant variance in the resource allocation between the resource plan (committed work) and the project plan (work assignments), you will have to work to optimize the schedule, cut scope, or negotiate for additional resources or changed dates to remain aligned to the committed work approved by the respective line managers.

To align project requests to the project schedule:

  1. From the Resources Grouping tab, open the Resource Plan tab.

  2. Align the resource request to the project schedule by adjusting the requested hours in the P for Proposed column for each time period and extend the duration of the requests as needed to align to the project schedule.

  3. Replace an existing resource by clicking the ellipsis (…) to the left of the resource to be replaced and select Change Resource and search for and select the replacement resource.

  4. Adjust the hours required for the replacement resource per time period in the P for Proposed column.

  5. Add new resources as needed by searching for and selecting them using the second search box. 

  6. Define the hours requested for the new resource per time period in the P for Proposed column.

  7. Once you have completed all resource request updates, click Submit and Save from the bottom right-hand corner of the form.


    Important: If you have project resource requests that are not currently visible on the form, you should use the drop down arrow and select Submit all periods and Save.

  8. Once the resource managers review and update the resource requests, you should then review and validate that all requests have been approved in the C for Committed column via the green shading or rejected/changed via the red shading


    Important: You should validate that you can be successful delivering the project based on the approved requests or work with your stakeholders and the resource managers to replan the project to satisfy both the project’s requirements and the availability of resources to complete the project work. 

Download Job Aid: Tracking project progress


Disclaimer: Some images in the instructional video and text instructions contained herein may appear different from (or not available) in your organization’s Sensei IQ instance due to specific custom configurations and/or continuous solution updates. Ensure that you are already an enabled user in the Sensei.IQ for Project application and check out the What’s New page. Contact your system administrator for any assistance.