To ensure that all the work identified in the project schedule is complete, it is important that the right resources, based on skills and availability, are assigned to each task. While the project schedule allows you to assign multiple resources to a project task, we recommend where possible that a single resource is assigned to a task.
To assign resources:
Assign resources in the timeline view
- Ensure you have the appropriate project open in Project for the web and ensure you are in the Timeline view.
- Hover your mouse to the immediate left of the Gantt bar left hand border to show the hidden add resource icon and click it.
- Search for and add the team member(s) to the task.
Assign resources in the board view
- Ensure you have the appropriate project open in Project for the web and ensure you are in the Board view.
- Hover your mouse over the card to show the ellipsis (…) and click on it and then select Assign task.
- Search for and add the team member(s) to the task.
Assign resources grid view
- Ensure you have the appropriate project open in Project for the web and ensure you are in the Grid view.
- Ensure that the Assigned to column is visible.
- Select Add column to add Assigned to if needed.
- Click in the Assigned to column and select the Add Resource icon
- Search for and add the team member(s) to the task.
Tip: To learn more about schedule management using Project for the web, click here.
Download Job Aid: Creating the project schedule in Project for the web
Disclaimer: Some images in the instructional video and text instructions contained herein may appear different from (or not available) in your organization’s Sensei IQ instance due to specific custom configurations and/or continuous solution updates. Ensure that you are already an enabled user in the Sensei.IQ for Project application and check out the What’s New page. Contact your system administrator for any assistance.