Create and maintain resource calendars (02:06)

Try It!

Resource Calendars will be utilized as needed to over-ride the enterprise calendar on a resource-by-resource basis. 


To create and maintain resource calendars:

  1. Ensure you are in the Resources area, click Resources in the Resources section.

  2. Select and edit the resource for whom you wish to create a calendar exception.

  3. Ensure you are editing the correct Resource and are on the Calendar Exceptions tab.

  4. Click an existing calendar exception and then More details to update it or Delete to remove it; or click New Calendar Exception to create a new one.

  5. Give the calendar exception a meaningful name.

  6. Define the From and To Dates for the exception.

  7. Click Save to update the enterprise calendar.


Download Job Aid: Creating and Maintaining Calendars


Tip: Refer to this extended version of the job aid for a more detailed guide on creating and maintaining enterprise calendars in Sensei IQ: Job Aid: Creating and maintaining enterprise calendars.


Disclaimer: Some images in the instructional video and text instructions contained herein may appear different from (or not available) in your organization’s Sensei IQ instance due to specific custom configurations and/or continuous solution updates. Ensure that you are already an enabled user in the Sensei.IQ for Project application and check out the What’s New page. Contact your system administrator for any assistance.