Update schedule (02:49)

Try It!

Every week, we must validate that the team member progress updates are applied to ensure that the schedule reflects work completed to date as well as validate the estimate for the remaining work to complete each task. Then, we need to review the schedule and take appropriate corrective actions to resolve any schedule slippage due to the progress updates from the team members.

Important: Depending on the execution tool that is linked to your project in Project IQ, refer to any of these external resources to update your project schedule:

  • If your project is linked to a Project for the web schedule, click here to learn how to build and maintain the schedule.
  • If your project is linked to a Project Online schedule, click here to learn how to build and maintain the schedule.
  • If your project is linked to a Jira scheduler, click here to learn how to build and maintain the schedule.
  • If your project is linked to an Azure DevOps plan, click here to learn how to build and maintain the plans.



To update the schedule using Sensei IQ’s native scheduling tool:

1. Track task progress

  1. Mark tasks as complete by clicking in the circle, in any view: Board, or Timeline

  2. Drag and drop a task to the Completed column in the Board/Progress view.

  3. Ensure the % complete column is visible in the Timeline view and enter the updated % complete directly in the column.

  4. In any view, click the “i” icon to open the task details pane and enter the updated status in the % complete field.

  5. Ensure the Effort completed, and Effort remaining columns are visible in the Timeline view and enter the updated actual and remaining effort directly in the columns.


    Important: Updating Effort completed will automatically update Effort remaining based on the total Effort for the task. Updating Effort remaining will automatically update the total Effort.

  6. Click the “i” icon in any view to open the task details pane and enter and enter the updated actual and remaining effort directly in the appropriate fields.


    Important: Updating Effort completed will automatically update Effort remaining based on the total Effort for the task. Updating Effort remaining will automatically update the total Effort.

2. Mark milestones as complete

  1. Review the project schedule and update any project milestones that were completed in the status period.

  2. Mark milestones as complete by clicking in the circle, in any view: Board, or Timeline. 

3.  Reschedule incomplete work in the past

  1. In the Timeline view, search for light blue Gantt bars to the left of the current date.

  2. Drag the timeline bar to reschedule this work to begin (continue) no earlier than the current date. 

Download Job Aid: Tracking project progress


Disclaimer: Some images in the instructional video and text instructions contained herein may appear different from (or not available) in your organization’s Sensei IQ instance due to specific custom configurations and/or continuous solution updates. Ensure that you are already an enabled user in the Sensei.IQ for Project application and check out the What’s New page. Contact your system administrator for any assistance.