Estimate the work in Project for the web (03:01)

Try It!

The key to successful estimating the work is to know what you’re estimating; effort or duration as well as the number of resources and the project schedule will always calculate the third.  You must define either the effort or the duration and the resources.


To estimate the work:

Estimating the work in the grid view

  1. Ensure you have the appropriate project open in Project for the web and the Grid view selected.

  2. Ensure that you have the Effort and Duration columns visible.

  3. Click Add column to add one or both columns as needed.

  4. Enter the task estimate in the Effort column based on estimating the amount of work required to complete the task or

  5. In the Duration column based on estimating how long the task will take.

Estimating the work in the task pane

  1. Ensure you have the appropriate project open in Project for the web.

  2. In any view, hover your mouse over a task to activate the ”i” icon and select it to open the task pane.

  3. Enter the task estimate in the Effort remaining box based on estimating the amount of work required to complete the task or

  4. In the Duration box based on estimating how long the task will take.



    Tip: To learn more about schedule management using Project for the web, click here.

Download Job Aid: Creating the project schedule in Project for the web


Disclaimer: Some images in the instructional video and text instructions contained herein may appear different from (or not available) in your organization’s Sensei IQ instance due to specific custom configurations and/or continuous solution updates. Ensure that you are already an enabled user in the Sensei.IQ for Project application and check out the What’s New page. Contact your system administrator for any assistance.